McKinley Street Grade Separation

Description: Construct a new four-lane overhead grade separation.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Riverside
City Corona
Zip Code 92882
 
Senate District
31
Assembly District 60
Congressional District 42
 
Caltrans District
08
 
 
County/State Route Riverside 91
Postmile Begin/End 9.2 9.2
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  235806      
MPH Increase in Project Area  1.6      
Pavement Lane Miles  3.75      
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Corona Savat Khamphou 951-279-3604   Savat.Khamphou@CoronaCA.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$2,876 $0 $2,876
Non-bond Funding
State/Federal*
$15,300 $0 $15,300
Local**
$94,250 $16,021 $110,271
 
Total**** $112,426 $16,021 $128,447

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,694 $0 $1,694 $1,112 $1,112 $582
Design(PS&E)
$11,183 $0 $11,183 $9,037 $9,037 $2,146
Right of Way
$28,517 $6,832 $35,349 $17,852 $17,852 $17,497
Construction
$71,032 $9,189 $80,221 $17,571 $17,571 $62,650
 
Total* $112,426 $16,021 $128,447 $45,572 $45,572 $82,875

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/18/2018 

03/28/2019 
 

 
07/18/2018 

03/28/2019 
100  07/18/2018 

03/28/2019 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/18/2018 

07/10/2021 
 

 
07/18/2018 

07/10/2021 
100  07/18/2018 

07/02/2021 


Begin Right of Way Phase

End Right of Way Phase
01/31/2019 

07/10/2021 
 

 
01/31/2019 

07/10/2021 
100  01/31/2019 

09/02/2021 


-2 
Begin Construction Phase

End Construction Phase
09/01/2021 

06/30/2023 
 

 
09/01/2021 

06/30/2023 
50  11/17/2021 

01/01/2024 
-3 

-6 
Begin Closeout Phase

End Closeout Phase
07/07/2023 

09/04/2025 
 

 
07/07/2023 

09/04/2025 
01/02/2024 

12/31/2024 
-6 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 235806
MPH Increase in Project Area 1.6
Pavement Lane Miles 3.75
System Enhancement 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.